Downtime & Quality Report

ABE PA – 4th Shift · June 2026 · Alpha and Bravo line downtime analysis

June 2026 · 375 hrs combined DT
Combined June DT

375 hrs

Alpha + Bravo lines

Alpha DT

158 hrs

Top: WSHE DT

Bravo DT

217 hrs

Top: WSHE DT

WSHE Restriction

115 hrs

Alpha + Bravo combined

Process / QA

95 hrs

Quality holds combined

Alpha Line Downtime

June 2026 · 158 total hours

PROCESS/QA
43h
ELECTRICAL
10h
MECHANICAL
14h
WSHE
53h
CLEANING
10h
PREVENTIVE MAINTENANCE
28h

Bravo Line Downtime

June 2026 · 217 total hours

PROCESS/QA
52h
ELECTRICAL
10h
MECHANICAL
5h
WSHE
62h
CLEANING
30h
PREVENTIVE MAINTENANCE
58h

Downtime Category Comparison – Alpha vs Bravo

June 2026 · side-by-side hours per category

Alpha Line
Bravo Line

June 2026 – Shift Remarks Timeline

90 shifts shown · Alpha 142h DT · Bravo 201h DT

Shift:
Category:
OPERATIONAL
WHSE RESTRICTION
PREV. MAINTENANCE
PROCESS/QA
CLEANING
MECHANICAL
ELECTRICAL
Date
Shift
Alpha DT
Alpha Remark
Bravo DT
Bravo Remark
6/1/261ST8hWHSE RESTRICTION8hWHSE RESTRICTION
6/1/262ND8hWHSE RESTRICTION8hWHSE RESTRICTION
6/1/263RD8hWHSE RESTRICTION8hWHSE RESTRICTION
6/10/261ST1hPROCESS/QAOPERATIONAL
6/10/262NDOPERATIONAL7hPREV. MAINTENANCE
6/10/263RDOPERATIONAL8hPREV. MAINTENANCE
6/11/261STOPERATIONAL8hPREV. MAINTENANCE
6/11/262NDOPERATIONAL2hPROCESS/QA
6/11/263RD2hWHSE RESTRICTION6hWHSE RESTRICTION
6/12/261ST1hPROCESS/QA1hWHSE RESTRICTION
6/12/262NDOPERATIONALOPERATIONAL
6/12/263RDOPERATIONAL1hPROCESS/QA
6/13/261STOPERATIONAL1hPROCESS/QA
6/13/262NDOPERATIONAL1hPROCESS/QA
6/13/263RD1hWHSE RESTRICTIONOPERATIONAL
6/14/261STOPERATIONALOPERATIONAL
6/14/262ND1hPROCESS/QA1hWHSE RESTRICTION
6/14/263RDOPERATIONALOPERATIONAL
6/15/261STOPERATIONALOPERATIONAL
6/15/262NDOPERATIONAL2hPROCESS/QA

Showing 120 of 90 shifts